home   |   concrete cutting   |   projects   |   equipment   |   about us   |   contact    
         

PAST PROJECTS

Past Projects

The Cross City Tunnel

As part of the Cross City Tunnel project which links the Eastern suburbs of Sydney to the Western, extensive modification to the abutment of the Art Gallery Rd. Bridge had to be undertaken to increase the width of the feeder road from Sir John Young Crescent to the Cahill Expressway/Harbour Tunnel.

The first part of the project was to dig out behind the existing abutment and construct a new abutment. The second stage was transferring the weight of the bridge from the original to the new abutment and the third stage was removing the original abutment.

ECR International was asked to scope the project by the tunnel’s constructors Baulderstone Hornibrook Bilfinger Berger Joint Venture. The abutment consisted of five columns each 5.3 metres high by 600mm wide and between 1.4 metres and 1.2 metres in width. Between each column was a 200mm. thick curtain wall. The weight of each column was about 10.3 tonnes and of each section of curtain wall about 5.3 tonnes. In total there was just under 73 tonnes of concrete to be removed. As the work was being carried out within one metre of the carriageway, the carriageway had to be closed and that was only possible between 10.00pm and 5.00am.

The first stage of the project was to drill lifting holes in the curtain wall, and then pre-cut the wall using a wall saw. After the wall had been pre-cut, a crane was bought and the crane’s chains were threaded through the lifting holes. The final cut was made that freed the section of wall being removed and the two tonne section of wall was removed. This process was repeated until all of the curtain wall had been removed.

The five columns were now exposed. Each column was divided into four pieces, the top piece weighing just less than one tonne, and the bottom piece weighing three tonnes.

The first stage of the process was for lifting holes to be drilled. As we were using a wire saw to cut the columns to size, wire holes, which are about 30mm. in diameter, had to be drilled in the appropriate places. We then cut all the horizontal lines. The columns were held in position by the new abutment. A crane was then bought in and hooked up to the top (one tonne) portion of the column. This portion was then cut vertically to separate it from the new abutment and then removed. As there was very little head room, and there were some tunnel services adjacent to the work area, removing these top sections was difficult, but using an expert crane company allowed the process to be completed without incident. After the top pieces had been removed, it was then a relatively easy task to remove the remaining sections of column sequentially.

Click here to download pdf detail sheet (pdf~312kb)