Removal of Turbine Foundation in Indonesia

This job required for the removal of the top 2.7 metres of a 9 metre high by 12 metres long by 6 metres wide turbine foundation.

The top table had a perimeter beam of 1.2metres by 1.2 metres, which was corbelled to the support legs that were of similar dimensions. There was 180 tonnes of concrete to be removed with no section to weigh more than 25 tonnes.

A Holer EWS 36 wire saw was selected for the job. There was a total of just over 32 square metres of cutting with 30no. 32mm. diameter reinforcing rods in each square metre of cutting. The job took eight days to complete. In addition, 150mm. diameter lifting holes were drilled through the beams, as well as 150no. 22mm. diameter by 650mm. deep starter bar holes. The starter bars were epoxied into the holes.